NRSWA Section 50

You will need a Section 50 licence if you need to place or retain apparatus in or on the highway. You must ensure all planning conditions are met as a Section 50 licence does not overrule any planning constraints.

All applications must be submitted at least one month in advance of the commencement of the proposed works. Where a Temporary Traffic Regulation Order (TTRO) is required, such as a road closure, you will need to adhere to the required timescales.

If you are connecting to an underground apparatus, please make sure you have the required permissions.

If anything changes during your works, it is your responsibility to keep us informed. This is particularly important if your works are likely to overrun the scheduled end date.

Fees

Section 50 licence

The cost of a Section 50 licence is:

  • £650 to install a new apparatus (SWL02)
  • £450 to work on an existing apparatus (SWL03).

Retrospective Section 50 licence

The cost of a retrospective Section 50 licence is:

  • £812.50 to install a new apparatus (SWL02)
  • £562.50 to work on an existing apparatus (SWL03).

Applying for a licence

To make an application, you need to obtain or provide:

  • an approved Temporary Traffic Regulation Order and temporary traffic signals (if required)
  • a plan showing the extent of proposed works (marked in red)
  • a copy of a valid public liability insurance certificate for a minimum of £10 million
  • a Traffic Management Plan
  • supervisor and operatives street works accreditation approval to submit
  • approval from the owner of the apparatus you are connecting to.